Phasing of Neighbourhood 1

July 2013

commence masterplanning and infrastructure delivery plan for whole site

July 2014

Adopt Local Plan and Lighthorne Heath Development Brief and masterplan

September 2014

Submit phase 1 planning application which will comprise:

December 2014

approval of Phase 1

June 2015

approval of first reserved matters application

2016 - 2017

100 dwellings

2017 - 2018

100 dwellings Primary school (form 1)

2018 - 2019

200 dwellings Country park and proportion of sports facilities + foul sewer upgrade

2019 - 2020

200 dwellings + local retail and health facilities

2020 - 2021

200 dwellings

2021 - 2022

200 dwellings

2022 - 2023

200 dwellings

2023 - 2024

200 dwellings

2024 - 2025

100 dwellings + Primary School form 2

2025 - 2026

100 dwellings